Understanding Construction Contract Prices: Navigating Changes and Exclusions
Building a new home or investment property is exciting, and a big part of that journey is understanding the contract price. It's easy to assume the price on your construction contract is fixed, but there are a few things that can cause it to change.
We're here to guide you through these potential shifts in the HIA Construction Contract and the Master Builders Construction Contract, keeping in line with the Queensland Building and Construction Commission (QBCC) standards.
Getting to grips with what can cause your contract price to increase is crucial. It's not just about budgeting; it's about being well-informed and prepared for the building proccess. Let's break down these factors and make sense of how your contract price might change.
Understanding Fixed Contract Prices

When you sign a construction contract, particularly for a big project like a new home or a duplex, you'll notice a number that stands out: the contract price. This is the amount you agree to pay for the construction work. In contracts like those from HIA or Master Builders, this price is usually fixed, and it's usually displayed prominently toward the front of the contract schedule. But what does "fixed" really mean?
In the world of construction, a fixed contract price is like a promise – it's the builder's commitment to complete the specified work for a specific amount. But, as with any promise, there are conditions. If the contract price isn't fixed, the method for calculating it, including any allowances, must be stated clearly in the contract. This is important because allowances, which are estimates for certain parts of the work, can sometimes end up costing more than expected.
There are stipulations for these, and specific names for these: Provisional Sum Items and Prime Cost Items. (We will be discussing these in a follow up post).
The catch is that the contract must also warn you about any conditions that might change this price. Things like unexpected site conditions, special stipulations from government authorities, and design alterations can all lead to adjustments in the final price. So, while the term 'fixed' might sound absolute, in practice, it's a bit more flexible.
Impact of Variations on Contract Price
Imagine this: You're halfway through your home build, and you decide that the bathroom tiles you originally picked just aren't cutting it. Or maybe you want to change the layout of the walls in the master bedroom, or the location of a window. These changes are what we call 'variations' in the construction world.
Variations are pretty common in building projects. They can be anything from a small tweak in the design to a complete overhaul of a section of the project. But here's the thing – every variation can potentially affect your contract price. The reason? Every change, no matter how small, can have a ripple effect on materials, labor, and even the timeline of your project.
In HIA and Master Builders contracts, any change to the materials used or work to be done is officially a variation. And the rule is clear: all variations must be agreed upon in writing by you, the homeowner, before any of that variation work begins. This is a safeguard for you – it keeps you in the loop and prevents any unexpected charges.
Extensions of Time (EOTs) and Their Consequences

In construction, adhering to the timeline is a critical aspect of the contract. However, sometimes unforeseen circumstances necessitate a change in schedule. This is where Extensions of Time (EOTs) become relevant.
EOTs are adjustments to the project timeline and can be requested by the contractor under certain conditions, such as changes made to the project (variations) or unexpected delays, including weather-related ones, or the Christmas shutdown period over December and January.
When a builder requests an EOT, they will provide you with a written claim. It's important to carefully review this claim and respond in a timely manner (the requirements for this timeframe are in the contract). If you agree to the EOT, the Date for Practical Completion is extended accordingly. However, if you disagree, the extension becomes a matter for dispute resolution.
Exclusions and Additional Requirements
Navigating the details of your construction contract is crucial, especially when it comes to understanding what's not included in the fixed price. These exclusions and additional requirements can significantly impact your budget.
Exclusions are elements not covered within the contract's fixed price. For instance, local council or state government development approvals and related fees are typically excluded, falling under the homeowner's responsibility. It's important to be aware of these exclusions to prevent unexpected costs during the construction process.
At Builders Brisbane, we stipulate that these items are excluded, unless already paid for as part of your preliminary agreement (which has a detailed breakdown when you start your journey with us).
Moreover, additional requirements often emerge as the project progresses. For example, you might find that the water connection to your site needs an upgrade, or you're required to extend the NBN service from down the road to your property. These kinds of requirements, sometimes not initially covered in the contract, will be considered variations and charged extra, adding to your overall project cost.
Conclusion
Understanding the ins and outs of your construction contract is more than just dotting the i's and crossing the t's. It's about getting a clear picture of what you’re signing up for, especially regarding the contract price. Knowing the full scope and where responsibility falls for certain items is very important.
There are many builders who will try to sign you up to a building contract before they go through their 'gallery' selections process and tend to exploit the fact that their plans might come with very basic specifications (a single batten light per room for example). Once you've signed the building contract, its hard to back out and so you might be 'locked in' to get the upgrades that you thought came as standard (such as LED downlights).
To be perfectly frank, you don't HAVE to sign a building contract before you are comfortable. If you do feel like you have signed a contract and then realised there was something not included or specified after the fact, there is a cool-off clause included by law in Queensland.